Operation Schedule of Indus-1 & Indus-2

 

Indus Operation Schedule: August 2016 to February 2017
30 June 2016 - 27 August 2016 Machine operation (Round-the clock), for users
28 August 2016 - 31 August 2016 Shutdown for Maintenance
1 September 2016 - 29 October 2016 Machine operation (Round-the clock), for users
30 October 2016 - 2 November 2016 Shutdown for Maintenance
3 November 2016 - 2 January 2017 Machine operation (Round-the clock), for users
3 January 2017- 8 January 2017 Shutdown for upgradation/maintenance
9 January 2017 - 28 February 2017 Machine operation (Round-the clock), for users